Cost performance index (CPI)
The cost performance index (CPI) is a measure of the financial effectiveness and efficiency of a project. It represents the amount of completed work for every unit of cost spent.
As a ratio, it is calculated by dividing the budgeted cost of work completed or earned value, by the actual cost of the work performed.
For example, if a project has a earned value (EV) of £20,000 but actual costs (AC) were £12,000:
CPI = EV / AC = 20,000 / 12,000 = 1.66
If the ratio has a value higher than 1 then it indicates the project is performing well against the budget. A CPI of 1 means that the project is performing on budget. A CPI of less than 1 means that the project is over budget.
[edit] Related articles on Designing Buildings Wiki
Featured articles
Check out some of the best features and news from Designing Buildings as well as key stories from around the web.
CIAT responds to Climate Change Committee report
An urgent wake-up call for both government and the built environment.
Construction Management, 24 June
FMB pilot aims to build pipeline of site-ready tradespeople.
A quick introduction.
CLC publishes Mental Health Joint Code of Practice.
A quick introduction to its uses and risks.
Construction Management, 17 June
Government rolls out digital planning tool to all local authorities.
Your views needed - a strategy for the professions, trades and occupations.
Confronting competency, codes, capacity and costs.
The hidden risk in modern construction supply chains.
Construction Management, 10 June
24 months to 14: CITB launches accelerated apprenticeships.
Bridging the gap between clients and contractors
Concerns remain around contractor quality, capability, and delivery.

















Comments
Bravo, que palabras..., el pensamiento magnfico volveremos al tema https://mixfilesmaker.com/